| What: |
International Mall Branch Library |
| Where: |
10315 NW 12th Street |
| Building Size: |
7,500 square feet |
| Estimated Construction Completion: |
March 2008 |
| Estimated Opening Date: |
May 2008 |
| Estimated Cost: |
$ 4 million. Second library to be built since the Main Library opened in 1985. |
| Computers: |
26 PC's & 12 laptops in a WiFi environment. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
| Special Features: |
Green space (canopied outdoor area to be used for story time and special programs during the cooler months). Patrons can use their laptops, with free WiFi, after hours. Interior of building has lots of open space and plenty of windows to create a bright and inviting atmosphere. Special area for young adults and a children's room. Unlike the stationary units that currently exist in other branches the shelving will be moveable to allow for re-configuration. |
| Construction Progress: |
 |
|
 |
| What: |
Kendale Lakes Branch Library |
| Where: |
15205 SW 88 Street |
| Building Size: |
15,000 square ft. |
| Estimated Opening Date: |
Fall 2008 |
| Estimated Cost: |
$ 7 million |
| Computers: |
32 PC's & 20 laptops in a WiFI environment. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
| Special Features: |
Situation directly on North Kendall Drive, this branch will feature a unique window display which will be used to showcase book displays and upcoming special events. As you enter the building, areas of the walls are accented by stone tiles and a large gallery wall which will display art exhibitions. With an abundance of windows for natural light, the library is accented by the beautiful outdoor green space. The outside extension will have a canopy under which children programs will be held. In addition to the large children's room, the branch features ample "people space" for lap top use. A separate entrance to the auditorium will provide privacy for meetings and after hour events. Patrons can also use their laptops, with free WiFi, even after hours. Book shelves will be moveable to allow for re-configuration. |
| Construction Progress: |  |
|
 |
| What: |
Pinecrest Branch Library |
| Where: |
5835 SW 111 Street |
| Building Size: |
15,000 square ft. |
| Estimated Opening Date: |
Fall 2008 |
| Estimated Cost: |
$ 3.5 million - interlocal agreement between MDPLS and the City of Pinecrest |
| Computers: |
36 PC's & 20 laptops in a WiFI environment. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
| Special Features: |
The Library sits adjacent to the Pinecrest Community Center and is connected by a covered pathway. The large vaulted ceilings will offer an abundance of natural light where patrons can sit at café-style stools and use laptops. There will be a comfortable seating area for and the children's room is large and open. An auditorium properly equipped with sound will be available to hold meetings and events A gallery wall will display library artwork. With a great deal of open space and light, the space library will be bright and inviting. Unlike the stationary units that exist in other branches, shelving will be moveable to allow for re-configuration. |
| Construction Progress: |  |
|
 |
| What: |
Virrick Park Branch Library |
| Where: |
3255 Plaza Street |
| Building Size: |
3,100 square ft. |
| Estimated Opening Date: |
Summer 2008
Interlocal lease agreement between MDPLS and the City of Miami. |
| Computers: |
8PC's & 6 laptops in a WiFI environment. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
| Special Features: |
A beautiful stained glass motif throughout the branch integrates the design from the adjacent park. This branch focuses on children and incorporates the green area of the park. Patrons can also use their laptops, with free WiFi, even after hours. Special area for young adults and a children's room. Unlike the stationary units that exist in other branches, shelving will be moveable to allow for re-configuration. |
| Construction Progress: |  |
|
 |
| What: |
Naranja Branch Library |
| Where: |
14850 SW 280 Street |
| Building Size: |
7,500 square ft. |
| Estimated Opening Date: |
2009 |
| Computers: |
32 PC's & 20 laptops in a WiFI environment plus three print kiosks. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
|
 |
| What: |
Palmetto Bay Branch Library |
| Where: |
17641 Old Cutler Road |
| Building Size: |
7,500 square ft. |
| Estimated Opening Date: |
2009 |
| Computers: |
10 PC's & 10 laptops in a WiFI environment plus one print kiosk. |
| Self-checkout Terminals |
Patrons will be able to check out their own books. |
| Construction Progress: |
 |
| |